Join us!
Public Meeting
Wednesday, June 22
6:00 – 7:30 PM
Hosted via Zoom
Join us to hear more about the Salem Offshore Wind Terminal Project!
Visit www.salem.com/oswmeeting to pre-register for the event.
Join our next public meeting to learn more about the project’s design and permitting process
Wednesday, November 16, 2022
6:00 – 7:30 PM
Participe en nuestra próxima reunión pública para conocer más sobre el diseño del
proyecto y el proceso de permisos
Miércoles 16 de noviembre de 2022
6:00 – 7:30 PM
The Project
The proposed development will result in a terminal providing new heavy-lift deployment and logistics services for offshore wind operations on remediated, 42 acre waterfront property on the site of a former coal and oil-fired power plant in Salem Harbor. Under the anticipated project, the site will contain the following elements:
Two laydown yards will provide space for pieces of the wind turbines called “nacelles” and “towers.”
The transition yard will connect between the two laydown yards and provide additional storage.
This area is planned for pre-assembly, staging and loadout activities adjacent to the bulkhead and wharf.
area improvements will provide adequate landside and waterside structures for loading and unloading of vessels.
Several berth areas are anticipated to accommodate berthing and moorage of wind turbine installment vessels (WTIVs) for loadout operations as well as heavy transportation vessels (HTVs) for inbound deliveries.
Equipment such as transport vehicles and high-capacity cranes will be on site to assist in moving the wind blades and nacelles.



The Site
The proposed site is 42 acres of waterfront property in a Designated Port Area of Salem Harbor. The site history dates to the 1790s, and several development and land reclamation projects have resulted in the current site configuration. Most recently, the property was the site of a 750-megawatt (MW) coal and oil-fired power plant which encompassed the original 65-acre parcel.
The coal plant was demolished beginning in 2014 and a site environmental remediation effort was undertaken. The original 65-acre site has since been divided into two lots. Footprint Power has developed a new natural gas fired power plant on the 23-acre site identified as Lot 1. The remaining 42 acres of the original site, designated Lot 2, will be developed into the Salem Offshore Wind Terminal.
Phasing and Timeline
The Salem Offshore Wind Terminal will be developed of the course of two to three years. We anticipate the following timeline:
- Spring 2022 | Project Kick-off for Engineering and Permitting
- Spring / Summer 2023 | Engineering and Permitting Complete
- Summer 2023 | Construction Starts
- Winter 2024 / 2025 | Construction Competed & Terminal Opens
- Spring 2022: Project Kick-off for Engineering and Permitting
- Spring / Summer 2023: Engineering and Permitting Complete
- Summer 2023: Construction Starts
- Winter 2024 / 2025: Construction Competed & Terminal Opens
Note: There may be construction activities during engineering and permitting.